The 2023 maintenance dredge campaign is now complete. Humber Work Boats have successfully removed nearly 30,000m3 of silt from the marina basin and lifeboat pen ensuring deep water for all boats within the marina. Work to remove the Cutter-Suction dredger John M and ancillary parts were delayed due to inclement weather but the last low loader left this morning.

There is still a bit of boat moving to complete to get everyone back in their own berth which the team are tackling head-on. Meanwhile the piling project continues as well as plans to relocate the containers to provide us with a winter shelter for welding and small boat repairs.

Thank you to all our customers for your patience and understanding during these essential works we hope that you have not been inconvenienced. Finally, we are very happy to announce we are open for visiting boats.